Data network actions
Data network actions
Objective of the changes
The existing ETSI network electronics is made up of Cisco switches, with an age of 15 years and with 10 Mbps user access ports, this equipment has been suitable for teaching and researcher activity until last year, in which the great demand for streaming applications arising from the needs of teleworking and tele-teaching, during these two years of pandemic improvement.
Sensitive to such needs, the SIC, through the Communications Area, has decided the substitution of the current network equipment to get a speed of access to the user of 1GBPS and links to 10GPS core equipment, which is a very important qualitative and technical leap.
Date planned for actions
The substitution works are scheduled between July 19 and August 13, 2021. Although given the complexity of the changes and the high number of connections may slightly affect the forecasts.
Updated information of the works
Finished areas: All laboratories, 0A, 0b, 0c, 0d, 1a, 1b, 1c and 1d
str1 (core Plaza de América), Str2 (core laboratories), 2a, 2b, 2c, 2d, 3a, 3b 3c, 3d
Action zones: 3e
Action zones planned tomorrow:
Updated: August 19, 2021
Network incidents and requests
In the transitory period in which the equipment substitution work is carried out, the Telematic System of Incident Management and Requests of Network of the Web Portal, will not be available, to avoid interference with the work ongoing. Attention to network users will be maintained by telephone, with the following (provisional) protocol of action:
Areas with completion of completed equipment
- Incidents: The calculation center will serve telephone (86131) all incidents related to the network of areas in which the works have ended. At the end of the day a report will be sent to the SIC communications area to resolve together. Keep in mind that the calculation center performs, in this case, an intermediation work, but has no capacity to resolve.
- High and low and modifications: the calculation center cannot carry out this type of request until substitution work is finished and the new procedures are established. Until then, they can use the SOS forms ( https://sos.us.es ) existing for this purpose.
Areas in which it has not yet acted
The calculation center will serve telephone (86131) the incidents and requests of high, low and network modifications and will resolve them, as it has usually been done, as long as it does not affect or harm the work ongoing.
The existing ETSI network electronics is made up of Cisco switches, with an age of 15 years and with 10 Mbps user access ports, this equipment has been suitable for teaching and researcher activity until last year, in which the great demand for streaming applications arising from the needs of teleworking and tele-teaching, during these two years of pandemic improvement.
Sensitive to such needs, the SIC, through the Communications Area, has decided the substitution of the current network equipment to get a speed of access to the user of 1GBPS and links to 10GPS core equipment, which is a very important qualitative and technical leap.
The substitution works are scheduled between July 19 and August 13, 2021. Although given the complexity of the changes and the high number of connections may slightly affect the forecasts.
Finished areas: All laboratories, 0A, 0b, 0c, 0d, 1a, 1b, 1c and 1d
str1 (core Plaza de América), Str2 (core laboratories), 2a, 2b, 2c, 2d, 3a, 3b 3c, 3d
Action zones: 3e
Action zones planned tomorrow:
Updated: August 19, 2021
In the transitory period in which the equipment substitution work is carried out, the Telematic System of Incident Management and Requests of Network of the Web Portal, will not be available, to avoid interference with the work ongoing. Attention to network users will be maintained by telephone, with the following (provisional) protocol of action:
Areas with completion of completed equipment
- Incidents: The calculation center will serve telephone (86131) all incidents related to the network of areas in which the works have ended. At the end of the day a report will be sent to the SIC communications area to resolve together. Keep in mind that the calculation center performs, in this case, an intermediation work, but has no capacity to resolve.
- High and low and modifications: the calculation center cannot carry out this type of request until substitution work is finished and the new procedures are established. Until then, they can use the SOS forms ( https://sos.us.es ) existing for this purpose.
Areas in which it has not yet acted
The calculation center will serve telephone (86131) the incidents and requests of high, low and network modifications and will resolve them, as it has usually been done, as long as it does not affect or harm the work ongoing.